Electric Boat Seaplane Ramp Demolition

Project
Electric Boat Seaplane Ramp Demolition
MARKETS
Marine
Demolition
CONTRACT TYPE
Prime Contractor
PROJECT OWNER
Quonset Development Corp
LOCATION
North Kingstown, RI
Printable PDF
Quonset Development Corporation contracted Manafort Transit to demolish an existing seaplane ramp in North Kingston, RI. The work consisted of installation and maintenance of a turbidity barrier around the site, demolishing the 200 ft. long by 50 ft. wide reinforced concrete ramp which included the extraction of approximately 224 creosoted timber piles, 56 concrete pile caps, concrete beam between pile caps, and the concrete deck structure.
Access to the site from land to the water was not provided by the owner due to site restrictions. As a result, all materials, equipment, and debris had to be transported to and from the site via barges and tugboats.
Manafort served as the Prime Contractor for the project and self-performed all the work.